Old State Highway Pipeline Replacement Project


Joint Infrastructure Upgrades by PCWA and SPMUD

Placer County Water Agency (PCWA) and South Placer Municipal Utility District (SPMUD) are partnering to deliver vital infrastructure upgrades in the heart of Newcastle. This coordinated effort will replace aging water and sewer pipelines, improve fire protection, and restore the roadway surface along Old State Highway and Buena Vista Avenue—enhancing long-term service reliability and community resilience.

Project Overview

This joint project will modernize critical water and sewer infrastructure while minimizing disruption through coordinated trenching and paving. By working together, PCWA and SPMUD are reducing neighborhood impacts and delivering cost-effective improvements for shared customers.

Key Improvements Include:

  • Replacement of 1,654 feet of 8-inch water mains and 22 water service connections

  • Replacement of 1,700 feet of 6-inch sewer mains and 17 sewer lower laterals

  • Installation of 5 new fire hydrants

  • Restoration of 33,871 square feet of roadway with full-width grind and overlay in key areas

What to Expect During Construction

Work Hours: Monday–Friday, 7:00 a.m. – 5:00 p.m.

Traffic Impacts: Expect lane closures and delays along Old State Highway and Buena Vista Avenue. Alternating one-way traffic flows will be maintained using flaggers.

Expect delays while traveling through the construction zone. Motorists should consider alternate routes.

On-Street Parking: “No Parking” signs will be posted at least 24 hours in advance of work.

Outage Notifications: Door hangers and/or direct notices will be provided ahead of any water or sewer service interruptions.

Project Benefits

  • Improved water and sewer reliability for Newcastle residents
  • Enhanced fire protection with new hydrants
  • Safer, smoother roads through coordinated paving
  • Reduced long-term disruption through joint trenching and cost-sharing

News Release

Read the full announcement:

PCWA and SPMUD Partner on $2.4 Million Pipeline Project in Newcastle

Contact

Water: PCWA Project Manager

Heather Knutson

(530) 823-4951 | hknutson@pcwa.net

Sewer: SPMUD Project Manager

Carie Huff

(916) 786-8555 | chuff@spmud.ca.gov

Project Video

Coming soon!

Project Timeline

  • Potholing & Pre-Construction

    November – December 2025

  • Sewer Trenching & Installation

    March – May 2026

  • Sewer Service Tie-Ins

    May 2026

  • Water Trenching & Installation

    May – July 2026

  • Water Service Tie-Ins

    July – August 2026

  • Roadway Resurfacing

    August – September 2026

  • Estimated Completion

    September 2026

Project Map

Buena Vista Avenue Pipeline Replacement Map
SPMUD LogoIn partnership with the South Placer Municipal Utility District
PCWA Logo
144 Ferguson Road
P.O. Box 6570
Auburn, CA 95604

Mon. - Thurs., 8am - 5pm

(530) 823-4850

Mon. - Fri., 8am - 5pm



Also on

Copyright © 2025 Placer County Water Agency All Rights Reserved | Privacy Policy
Weather Provided by OpenWeather